Edmond Tower Update – June 23, 2025

June 16, 2025

The tower builders worked very hard the last couple days.  As of end of business today they hit 320 feet.  That’s as high as the crane can get.  They will use a gin pole starting tomorrow to get the last 80 feet installed.  The shelter should be delivered tomorrow and place on its foundation.  Soon we will have a fully functional radio tower.

Friday morning (June 13)
The bolts that hold the sections together.
Saturday midday (June 14)
Monday Morning (June 16)
Attaching the 300-320 foot section
The 320 foot mark – End of day Monday (June 16)

June 23, 2025

The shelter has been installed. They are hooking up electrical and installing antennas and feed lines this week. (June 23)

Ben, KJ5IEB

Leave a comment