The foundation was poured this week. It took 220 cubic yards of concrete. With the steel, rebar, and concrete the foundation weighs just under a million pounds. They will start packing earth in on top of the foundation this week. Stacking the tower segments should begin first week of June.














Ben, KJ5IEB